Project Schedule - September 2009 to September 2011
All schedule dates are subject to change and conditional upon resources and weather.
For more information on each Construction Step click on the step number above or the links below.
This project will:
- Replace the existing Woodmen Road/Academy Blvd. Intersection with a grade separated interchange which will raise Woodmen Road above Academy Boulevard.
- Provide three continuous lanes in each direction on Woodmen Road.
- Be constructed in eight steps. The first four steps will take place concurrently.
- Limit night work to activities requiring accommodation for maintenance of traffic and safety to workers and traveling public.
- Maintain two access points to shopping centers throughout construction.
- Be substantially complete by September 2011.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.