Project Schedule - September 2009 to September 2011

All schedule dates are subject to change and conditional upon resources and weather.Project Schedule - September 2009 to September 2011 Step 1 information Step 2 information Step 3 information Step 3 information Step 4 information Step 4 information Step 5 information Step 5 information Step 6 information Step 6 information Step 7 information Step 7 information Step 8 information Step 8 information

For more information on each Construction Step click on the step number above or the links below.


Step 1 | Step 2 | Step 3 | Step 4 | Step 5 | Step 6 | Step 7 | Step 8
 
Schedule Progress as of 9-1-10
This project will:

  • Replace the existing Woodmen Road/Academy Blvd. Intersection with a grade separated interchange which will raise Woodmen Road above Academy Boulevard.
  • Provide three continuous lanes in each direction on Woodmen Road.
  • Be constructed in eight steps. The first four steps will take place concurrently.
  • Limit night work to activities requiring accommodation for maintenance of traffic and safety to workers and traveling public.
  • Maintain two access points to shopping centers throughout construction.
  • Be substantially complete by September 2011.

 

Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.