Traffic and temporary alignments:

  • Traffic will remain on existing Woodmen Road between Campus Drive and Hobby Lobby while roadway is widened on north and south sides
  • Key activities:

  • Realign 30-inch sanitary sewer at Cottonwood Creek. Complete
  • Install 66-inch storm drain pipe and construct outfall structure beginning at Cottonwood Creek. Complete
  • Relocate existing utilities (throughout project area.) 90%
  • Excavate and move material from north side to south side of Woodmen between Campus Drive to Current access entrance. Remove median concrete. Complete
  • Grade and pave the anticipated temporary alignment through former Shell station area. Complete
  • Install portion of 42-inch water line under anticipated Woodmen Road detour. Complete
  • Construct retaining wall at Wag ’n Wash/Home Depot entrance. Complete
  • Construct concrete fence at Bell Drive. Complete
  • Construct retaining wall on Woodmen Road east of Academy Boulevard. Complete
  • Install storm drain on Prince Drive. Complete
  • Reconstruct detention pond on Current property. Complete
  •  

    All construction step dates are subject to change and conditional upon resources and weather.

     

    Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.