Construction Step 1
Click here or on the image for a detailed .pdf of Step 1
Traffic and temporary alignments:
Traffic will remain on existing Woodmen Road between Campus Drive and Hobby Lobby while roadway is widened on north and south sides
Key activities:
Realign 30-inch sanitary sewer at Cottonwood Creek. Complete
Install 66-inch storm drain pipe and construct outfall structure beginning at Cottonwood Creek. Complete
Relocate existing utilities (throughout project area.)
90%
Excavate and move material from north side to south side of Woodmen between Campus Drive to Current access entrance. Remove median concrete. Complete
Grade and pave the anticipated temporary alignment through former Shell station area.
Complete
Install portion of 42-inch water line under anticipated Woodmen Road detour.
Complete
Construct retaining wall at Wag ’n Wash/Home Depot entrance.
Complete
Construct concrete fence at Bell Drive.
Complete
Construct retaining wall on Woodmen Road east of Academy Boulevard.
Complete
Install storm drain on Prince Drive.
Complete
Reconstruct detention pond on Current property.
Complete
All construction step dates are subject to change and conditional upon resources and weather.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.