Construction Step 3
Click here or on the image for a detailed .pdf of Step 3
Traffic and temporary alignments:
Traffic will remain within the existing roadway alignment.
Key activities:
Construct Olga Willson Way. Complete
Construct Wildwood cul de sac. Complete
Grade and pave the temporary alignments west of existing intersection. Complete
Construct and tie-in 42-inch water line vaults under Woodmen Road temporary alignment area. Complete
Construct Academy temporary alignment.
Complete
Reconstruct Academy Boulevard between Mimi's Restaurant driveway and Shrider Road. 75%
All construction step dates are subject to change and conditional upon resources and weather.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.