Construction Step 5 April 2010 to September 2010


Woodmen Road Construction Step Five Detailed .pdf of construction step 5

Click here or on the image for a detailed .pdf of Step 5

Step 1 | Step 2 | Step 3 | Step 4 | Step 5 | Step 6 | Step 7 | Step 8

 

Traffic and temporary alignments:

  • Academy Boulevard traffic will remain on Academy temporary alignment. Woodmen Road traffic will shift to temporary alignment
  • Key activities:

  • Excavate for Academy Boulevard final alignment. 90%
  • Complete structural concrete on Woodmen Road Bridge. 60%
  • Construct embankment at east end of bridge, and retaining walls in southeast quadrant of intersection. 70%
  • Install storm drain on Academy Boulevard. 75%
  • Milestone:

  • Installation of 42-inch water line complete. Complete -
    Milestone Reached
  •  

    All construction step dates are subject to change and conditional upon resources and weather.

     

    Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.