Construction Step 7 - June 2011 to July 2011
Click here or on the image for a detailed .pdf of Step 7
Traffic and temporary alignments:
Woodmen Road traffic shifts to new bridge
Turning movements restricted for 14 days to allow for completion of ramps
- Westbound and eastbound Woodmen Road
to northbound Academy Boulevard
- Southbound Academy Boulevard to eastbound
and westbound Woodmen Road
Key activities:
Complete ramps at northeast and northwest quadrant of intersection using fast-track construction (day and night work)
Remove westbound Woodmen Road temporary alignment
Restore Woodmen Commons Shopping Center parking lot
Milestone:
Woodmen traffic is placed on bridge
All construction step dates are subject to change and conditional upon resources and weather.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.