Construction Step 8 - July 2011 to September 2011
Click here or on the image for a detailed .pdf of Step 8
Traffic and temporary alignments:
Academy Boulevard and Woodmen Road traffic on final alignment
Key activities:
Install rubberized asphalt on Woodmen Road
Complete Woodmen Road medians and final landscaping
Milestone:
Substantial completion of project September 2011
All construction step dates are subject to change and conditional upon resources and weather.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.